A plain, sourced summary of which federal disaster and mitigation programs are operating, which are in transition, and which requirements have not changed.

Written for tribal emergency managers, program directors, and capture teams who need to know what to plan around. No opinions, no advocacy, and every item linked to its primary source.

Elevated home with a gable wall torn open by hurricane winds
Field inspection: an elevated home with a torn gable wall.
Last reviewed October 5, 2026
Status board

Program by program

Federal disaster policy has moved a great deal since 2025. Most of the movement has been in how programs are delivered rather than in what the regulations require. The distinction matters, because a nation can lose eligibility by assuming a requirement went away with a program.

Tribal mitigation plan requirement

Unchanged

44 CFR 201.7 still requires a federally recognized tribe to have a FEMA approved Tribal Mitigation Plan as a condition of receiving non emergency Stafford Act assistance and FEMA mitigation grants as a recipient, and still requires review and update at least every five years. Nothing proposed to date removes that requirement.

Source: 44 CFR 201.7

Tribal Mitigation Plan Review Guide

2017 version operative

The 2017 guide remains FEMA's official tribal mitigation planning policy. FEMA has been updating it through government to government consultation since 2023 to align it with newer programs and strategies. Plans submitted now are reviewed against the 2017 guide. Check the policy update page before starting a plan.

Source: FEMA tribal mitigation planning policy updates

Local mitigation planning policy

Current

The Local Mitigation Planning Policy Guide, FP-206-21-0002, took effect April 11, 2025 and governs plans under 44 CFR 201.6. It applies where a tribe participates in a multi jurisdictional plan alongside local governments.

Source: FP-206-21-0002, effective April 11, 2025

Building Resilient Infrastructure and Communities

Restored, unsettled

Terminated April 4, 2025; ruled unlawfully terminated in Washington v. FEMA on December 11, 2025; reopened with a $1 billion FY2024 and FY2025 notice that ran March 25 to July 23, 2026, including a $50 million tribal set-aside and a $25 million tribal building code plus-up. That notice removed hazard mitigation planning from BRIC eligibility and limited capability and capacity building to project-linked work. No later round had been announced at review, and earlier selected projects remain partly unobligated. Full BRIC status and timeline.

Sources: FEMA BRIC page, CRS IN12609, Grants.gov

Hazard Mitigation Grant Program

Operating, reform proposed

HMGP continues to operate after major disaster declarations under 44 CFR Part 206 Subpart N, and up to seven percent of HMGP funding remains available for mitigation planning. The FEMA Review Council has recommended replacing HMGP with a rapid mitigation advance and a strategic mitigation allocation administered at the state level. That change would require action by Congress and has not occurred.

Source: 44 CFR 206.434 and the Review Council final report

National Flood Insurance Program authorization

Extended to Dec. 11, 2026

The NFIP operates on short-term extensions. Its authorization ran through September 30, 2026 and was extended through December 11, 2026 by a continuing resolution. If authorization lapses, FEMA cannot issue new policies or renew expiring ones, although existing policies stay in force and claims continue to be paid. Flood claim deadlines and Public Assistance insurance requirements do not change during a lapse.

Source: FEMA congressional reauthorization page

Tribal disaster declarations

Interim guidance in effect

The 2024 Tribal Declarations Interim Guidance, FP 104-009-025-001, took effect December 3, 2024 and replaced the 2017 Tribal Declarations Pilot Guidance. FEMA reissued it with updates in April 2025. Key terms include a $100,000 minimum damage indicator for a tribal Public Assistance declaration and an automatic recommendation for a 98 percent federal cost share once actual federal Public Assistance obligations reach $200,000. It is interim, meaning FEMA may revise it after reviewing comments filed under docket FEMA-2024-0035.

Source: FP 104-009-025-001, effective December 3, 2024

Preliminary damage assessment

2025 guide in effect

FEMA’s 2025 Preliminary Damage Assessment Guide governs local, state, tribal and joint damage assessments for incidents with incident periods beginning on or after July 1, 2025. The damage record built in the first days after an event drives the declaration request and later Public Assistance eligibility.

Source: FEMA PDA Guide, July 2025

Public Assistance policy

Version 5.0 Amended

PAPPG Version 5.0 Amended applies to incidents declared on or after January 6, 2025. Version 4 continues to govern incidents declared on or after June 1, 2020 and before that date. On any file, apply the version that matches the declaration date, not the current one.

Source: PAPPG V5.0 Amended, FP 104-009-2

FEMA reform

Report issued, legislation pending

The FEMA Review Council, established by Executive Order 14180, issued its final report on May 7, 2026 with ten recommendations. The Council's stated doctrine is that disaster response should be locally executed, state or tribally managed, and federally supported. Separately, H.R. 4669, the Fixing Emergency Management for Americans Act of 2025, was ordered reported by the House Committee on Transportation and Infrastructure on September 3, 2025, by a vote of 57 to 3. As of mid-2026 it had not passed the House and no Senate companion had been introduced. Among other changes, it would convert pre-disaster mitigation funding to formula grants and let tribes request Fire Management Assistance Grants directly. The most consequential recommendations, including changes to Public Assistance, Individual Assistance, and the National Flood Insurance Program, would require acts of Congress.

Source: Review Council final report and CRS analysis
The practical read

What has not changed

Whatever the delivery mechanism ends up being, four things have held constant through every proposal on the table.

  • An approved mitigation plan is still the eligibility gateEvery serious reform proposal keeps a planning requirement in front of mitigation funding. Nations without a current plan are outside the door regardless of which program is paying, even though BRIC itself no longer funds plan development.
  • Documentation still decides outcomesEligibility determinations, appeals, closeout, and audit all turn on the record. Shifting administration to the state or tribal level does not lower the documentation standard, and in most proposals it raises it.
  • Insurance still offsets federal assistanceSection 312 of the Stafford Act is statutory. Duplication of benefits analysis is required no matter which agency or level of government cuts the check.
  • More responsibility is moving toward tribes and states, not lessThe Review Council's stated doctrine is locally executed, state or tribally managed, federally supported. Read plainly, that means the administrative capacity a nation builds now is worth more later, not less.

How to use this page

Treat it as a starting point and a set of links, not as authority. Federal program status changes without notice, and a notice of funding opportunity on Grants.gov is the only thing that establishes that a program is open. Before committing a budget or a subapplication schedule, confirm against the primary sources below and with your FEMA regional office or state hazard mitigation officer.

This page is reviewed periodically and dated at the top. If you find something out of date, tell us and we will correct it.

Okla Risk Advisors tracks these changes as a tribal hazard mitigation plan consultant.

Official sources

Primary sources

Every item on the status board above traces to one of these. All are government or congressional sources.

Primary documents

Program pages to check before you plan around anything

Okla Risk Advisors is not a government agency and does not speak for FEMA, the Department of Homeland Security, or any tribal government. This page summarizes public documents and links to them. Where a summary and a source conflict, the source governs.

Need to know how this affects a specific nation or program?

Send the situation. You will get a direct read on what is required today, what is in motion, and what should be decided now rather than later.